Numbers you must memorize

TopicValue
Small appliance definitionFactory-sealed, 5 lb or less
Small appliance recovery — compressor works90% or 4 in. Hg
Small appliance recovery — compressor dead80% or 4 in. Hg
Passive (system-dependent) recoveryAppliances with 15 lb or less
Recovery cylinder fill limit80% by weight
High-pressure evacuation, HCFC-22 < 200 lb0 in. Hg
High-pressure evacuation, HCFC-22 ≥ 200 lb10 in. Hg
Other high-pressure < 200 lb / ≥ 200 lb0 / 15 in. Hg
Very-high-pressure (R-503, R-13)0 in. Hg
Low-pressure evacuation (post-11/15/93 equipment)25 mm Hg absolute
Low-pressure rupture disc15 psig
Low-pressure leak test pressure limit10 psig
Leak-rate thresholds (≥ 50 lb)Comfort cooling 10% · Commercial refrigeration 20% · Industrial process 30%
Leak repair deadline30 days (or mothball / retire)
Records retention3 years

Do not mix Type I percentages (80/90) with Type II vacuums (0/10/15 in. Hg) or Type III's 25 mm Hg absolute. That mix-up is how people fail one section at 17/25.

Dates

  • July 1, 1992 — venting of CFC/HCFC prohibited
  • November 15, 1993 — recovery equipment after this date must be certified; determines evacuation levels
  • November 14, 1994 — technicians must be certified
  • November 15, 1995 — venting prohibition extended to HFCs

Pick the right type before you memorize

  • Factory-sealed, 5 lb or less → Type I
  • Field-charged high-pressure (splits, rooftops, racks) → Type II
  • Low-pressure chillers → Type III
  • All three plus Core → Universal

Full comparison: EPA 608 Type 1 vs Type 2 vs Type 3. Passing is 18 of 25 (72%) per section — see the passing score guide. Who must sit: who needs EPA 608.

Study plan (two weeks)

  1. Days 1–3 — Core. Recite the dates, 80% cylinder fill, recover/recycle/reclaim, and the venting rule. Practice until 85%+.
  2. Days 4–6 — Type I. Small-appliance definition, 80/90% or 4 in. Hg, piercing valves, passive recovery.
  3. Days 7–9 — Type II. Flash-card the leak-rate table (10 / 20 / 30) and the evacuation table. Recover liquid first.
  4. Days 10–12 — Type III. Vacuum operation, 10 psig leak test, 15 psig disc, 25 mm Hg absolute, vapor-first charging.
  5. Days 13–14 — Mock exams. Timed mocks, review every miss, re-drill the weak category from your dashboard.